TRANSMISION NETWORKS
Name of Project |
TURNKEY CONSTRUCTION OF 154/11 kV BOSPHORUS TRANSFORMER SUBSTATION AND POWER TRANSMISSION LINE INST. 154 kV BOSPHORUS TS MANİSA-SALİHLİ PTL CONNECTION POINT 154 kV 2x1272 MCM |
1 |
| Place |
TURGUTLU - MANISA |
| Employer |
BOSPHORUS NICKEL MADENCİLİK TİCARET A.Ş. |
| Contract Date |
06.09.2006 |
| Completion Date |
06.09.2009 |
| Amount of Project (USD) |
5,800,000 |
| Name of Project |
TURNKEY CONSTRUCTION AND INSTALLATION OF 154 kV IĞDIR TRANSFORMER SUBSTATION REF NO.İTM.49 |
3 |
| Place |
IĞDIR |
| Employer |
TEIAS GENERAL MANAGEMENT |
| Contract Date |
10.10.2007 |
| Completion Date |
26.09.2008 |
| Amount of Project (USD) |
705,000 |
| Name of Project |
TURNKEY CONSTRUCTION AND INSTALLATION OF 154 kV MUŞ TRANSFORMER SUBSTATION REF NO.İTM.49 |
4 |
| Place |
MUŞ |
| Employer |
TEIAS GENERAL MANAGEMENT |
| Contract Date |
10.10.2007 |
| Completion Date |
26.09.2008 |
| Amount of Project (USD) |
670,000 |
| Name of Project |
TURNKEY CONSTRUCTION AND INSTALLATION OF 154 kV LARA-II TRANSFORMER SUBSTATION REF NO.İTM.50 |
5 |
| Place |
ANTALYA |
| Employer |
TEIAS GENERAL MANAGEMENT |
| Contract Date |
15.11.2007 |
| Completion Date |
26.12.2008 |
| Amount of Project (USD) |
5,180,000 |
| Name of Project |
TURNKEY CONSTRUCTION OF 154 kV SHUNT CAPACITOR BANKS IN 380 kV DENİZLİ,380 kV KONYA 4, 154 kV LARA-I, 380 kV UZUNDERE TRANSFORMER SUBSTATIONS REF NO: TKAPY.2 |
6 |
| Place |
DENİZLİ |
| Employer |
TEIAS GENERAL MANAGEMENT |
| Contract Date |
13.12.2007 |
| Completion Date |
23.07.2008 |
| Amount of Project (USD) |
4,112,000 |
| Name of Project |
TURNKEY CONSTRUCTION AND INSTALLATION OF 380 kV BATMAN-II TRANSFORMER SUBSTATION REF NO.İTM.51 |
7 |
| Place |
BATMAN |
| Employer |
TEIAS GENERAL MANAGEMENT |
| Contract Date |
18.12.2007 |
| Completion Date |
20.12.2009 |
| Amount of Project (USD) |
5,425,000 |
| Name of Project |
TURNKEY CONSTRUCTION AND INSTALLATION OF 380 kV KIZILTEPE-II TRANSFORMER SUBSTATION REF NO.İTM.52 |
8 |
| Place |
MARDİN |
| Employer |
TEIAS GENERAL MANAGEMENT |
| Contract Date |
18.12.2007 |
| Completion Date |
22.03.2009 |
| Amount of Project (USD) |
8,750,000 |
| Name of Project |
TURNKEY EXTENTION OF 154 kV GÖLKÖY SUBSTATION UNDER THE SCOPE OF DARICA-1 HEPP |
9 |
| Place |
GÖLKÖY,ORDU |
| Employer |
YAPISAN CO. |
| Contract Date |
08.04.2008 |
| Completion Date |
15.10.2008 |
| Amount of Project (USD) |
695,000 |
| Name of Project |
ELECTRICAL CONSTRUCTION-INSTALLATION BANDIRMA WIND ENERGY STATION |
10 |
| Place |
BANDIRMA |
| Employer |
BORASCO CO. |
| Contract Date |
17.03.2008 |
| Completion Date |
31.06.2009 |
| Amount of Project (USD) |
11,600,000 |
| Name of Project |
POWER TRANSMISSION LINE INSTALLATION TO BAHÇE WIND PARK, 154 kV, 2x954 MCM, 7 km |
11 |
| Place |
OSMANİYE, ADANA |
| Employer |
ZORLU ROTOR CO. |
| Contract Date |
12.06.2008 |
| Completion Date |
31.01.2009 |
| Amount of Project (USD) |
1,448,000 |
| Name of Project |
OPERATION OF 154 kV ALTINTAŞ,
SİMAV, KIRKA, EMİRDAĞ, BİLORSA
TRANS. SUB. GROUP NO: TMİ/4.6-1 |
12 |
| Place |
KÜTAHYA
ESKİŞEHİR
AFYON
BİLECİK |
| Employer |
TEİAŞ 6th DIR. OF TRANS. CONS.OPERATION |
| Contract Date |
15.03.2004 |
| Completion Date |
11.06.2009 |
| Amount of Project (USD) |
1,334,000 |
| Name of Project |
OPERATION OF 154 kV AKÇALAR,
BANDIRMA III, ERDEK, GÖBEL
TRANS. SUB. GROUP NO: TMİ/4.2-1 |
13 |
| Place |
BURSA
BALIKESİR |
| Employer |
TEİAŞ 2nd DIR. OF TRANS. CONS. OPERATION |
| Contract Date |
29.03.2004 |
| Completion Date |
25.06.2009 |
| Amount of Project (USD) |
1,000,000 |
| Name of Project |
OPERATION OF 154 kV ALÇUK,
ALMAK, HABAS TRANS. SUB.
GROUP NO: TMİ/4.3-3 |
14 |
| Place |
İZMİR |
| Employer |
TEİAŞ 3th DIR. OF TRANS. CONS. OPERATION |
| Contract Date |
22.04.2004 |
| Completion Date |
07.07.2009 |
| Amount of Project (USD) |
773,000 |
| Name of Project |
OPERATION OF 154 kV BURSA III, KESTEL,
YENİŞEHİR, M.KEMALPAŞA TRANS. SUB.
GROUP NO: TMİ/6.2-1 |
15 |
| Place |
BURSA |
| Employer |
TEİAŞ 2nd DIR. OF TRANS. CONS. OPERATION |
| Contract Date |
21.07.2005 |
| Completion Date |
18.10.2010 |
| Amount of Project (USD) |
1.246,000 |
| Name of Project |
OPERATION OF 154 kV VİKİNG, HİLAL(GIS+KLASİK), GÜZELYALI (GIS), KARŞIYAKA (GIS) TRANS. SUB.
GROUP NO: TMİ/8.3-1 |
16 |
| Place |
İZMİR |
| Employer |
TEİAŞ 3rd DIR. OF TRANS. CONS. OPERATION |
| Contract Date |
01.07.2007 |
| Completion Date |
03.09.2010 |
| Amount of Project (USD) |
775,000 |
| Name of Project |
OPERATION OF 154 kV YUNTDAĞ TRANS. SUB. AND WEPP |
17 |
| Place |
BERGAMA, İZMİR |
| Employer |
INNORES INC. |
| Contract Date |
01.03.2008 |
| Completion Date |
01.03.2011 |
| Amount of Project (USD) |
48,000 |
^ Top
|